A full renovation coordinates design, procurement and construction. This illustrative model covers a roughly 70–90 m² three-room apartment in 20 phases. Amounts are planning inputs, not current quotations. A final bill of quantities needs quantities, materials, tax basis and clear scope boundaries.
Before starting: documentation
The designer first classifies the actual intervention: routine maintenance, adaptation, investment maintenance or reconstruction. Work without an authority act, Article 145 approval and a building permit are different routes. A technical description cannot replace a preliminary design where required. Structure, façade and shared services need specific review. Work notification depends on the applicable procedure. Consult the linked guidance for current steps, and check house rules and notices for the municipality and building.
| Phase | Calendar days* | RSD |
|---|---|---|
| Design and preparation | 28 | 115 000 |
| Demolition and disposal | 10 | 120 000 |
| Masonry | 10 | 180 000 |
| Electrical first fix | 10 | 265 000 |
| Plumbing first fix | 7 | 250 000 |
| Heating and cooling | 10 | 350 000 |
| Windows and entrance door | 7 | 420 000 |
| Plaster and dry lining | 18 | 345 000 |
| Screed and waiting | 28 | 170 000 |
| Tiling and waterproofing | 14 | 360 000 |
| Skimming and primer | 10 | 120 000 |
| Painting | 10 | 190 000 |
| Floor finishes | 7 | 275 000 |
| Internal doors | 5 | 270 000 |
| Kitchen | 4 | 440 000 |
| Sanitary fittings | 5 | 300 000 |
| Electrical second fix | 5 | 170 000 |
| Fitted wardrobes | 5 | 280 000 |
| Cleaning | 3 | 55 000 |
| Handover | 3 | 0 |
| TOTAL | 199 | 4 675 000 |
Budget and contingency
RSD 4,675,000 includes RSD 115,000 for phase one; the remainder is RSD 4,560,000. This model has a different scope from the public calculator. Loose furniture, appliances, temporary accommodation and contingency are excluded. Check tax and scope in quotations. Link contingency to apartment-specific risks, especially concealed services and substrates.
Duration: a sum is not a completion date
*199 calendar days is the sum of individual planning durations and waiting, not 199 working days. Separate active work, drying, ordering and delivery in the Gantt chart. Overlap requires available space, crews and predecessors. Three to four months may be a scenario, not a promise. A screed is not ready for timber simply after 28 days: measure moisture and follow substrate, heating, adhesive and flooring requirements.
Concealment checks and handover
Before closing walls, record routes and positions, check services and retain test records. Inspect waterproofing before covering; select compatible boards, adhesives, tapes and grout. Drainage acoustics also depend on supports and penetrations. Flooring, doors and appliance ventilation follow selected-product instructions. Handover includes defects, rectification dates, manuals, warranties and test evidence.