Yes. For projects on Lists I and II, the Ministry’s opinion on the need to initiate the EIA procedure is obtained during the procedure for issuing location conditions.
Note: The opinion may also be obtained with location information or at the project developer’s request. It does not replace the appropriate procedure for a project on List I or II.
Original Serbian quotation
„За пројекте из члана 5. став 1. тач. 1) и 2) овог закона прибавља се мишљење министарства надлежног за послове заштите животне средине (у даљем тексту: Министарство) о потреби покретања поступка процене утицаја у поступку издавања локацијских услова у складу са законом којим се уређује планирање и изградња. Захтев за мишљење из стaва 1. овог члана може да се прибави и у поступку издавања информације о локацији. Министарство даје мишљење из става 1. овог члана и на захтев носиоца пројекта, односно подносиоца захтева. Захтев за мишљење из ст. 1–3. овог члана садржи: 1) податке о носиоцу пројекта, односно подносиоцу захтева; 2) назив пројекта и све планиране делове пројекта и/или фазе изградње; 3) податке о локацији, односно о катастарским парцелама на којима се планира пројекат; 4) податке о физичким карактеристикама пројекта (површина, дужина, капацитет у складу са специфичностима пројекта). Мишљење из ст. 1–3. овог члана не ослобађа носиоца пројекта из члана 5. став 1. тач. 1) и 2) овог закона обавезе да покрене поступак процене утицаја на животну средину.”
Informational English translation of the quotation
For projects referred to in Article 5, paragraph 1, items 1) and 2) of this law, an opinion of the ministry responsible for environmental protection (hereinafter: the Ministry) on the need to initiate the impact assessment procedure shall be obtained in the procedure for issuing location conditions in accordance with the law governing planning and construction. The request for an opinion referred to in paragraph 1 of this Article may also be obtained in the procedure for issuing location information. The Ministry also gives the opinion referred to in paragraph 1 of this Article at the request of the project developer or applicant. The request for an opinion referred to in paragraphs 1–3 of this Article contains: 1) information about the project developer or applicant; 2) the project name and all planned parts of the project and/or construction phases; 3) information about the location, or the cadastral parcels on which the project is planned; 4) information about the physical characteristics of the project (area, length, capacity in accordance with the specifics of the project). The opinion referred to in paragraphs 1–3 of this Article does not release the project developer referred to in Article 5, paragraph 1, items 1) and 2) of this law from the obligation to initiate the environmental impact assessment procedure.Informational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- If I have received an opinion in the location conditions, does that complete my EIA obligation?No. The opinion alone does not release the project developer from the obligation to initiate the EIA procedure when the project…
- Koji projekti su izuzeti od primjene EIA zakona?Isključivo suzbijanje neposredne opasnosti po život, zdravlje ili imovinu i spašavanje, samo tokom okolnosti utvrđenih posebnim…
- Must the EIA procedure be completed before the construction permit or other project approval?Yes. When EIA applies, the procedure is carried out before approval for carrying out the project is issued.
- Is there a separate list of projects for which an EIA is mandatory?Yes. The Government prescribes List I of projects for which an impact assessment is mandatory.
- What does the law provide for projects for which a full EIA is not automatic?For List II, an application for a decision on the need for an assessment must be submitted; the competent authority decides by…
- Ko vodi postupak procjene uticaja?Ministarstvo vodi projekte Liste I, navedene IPPC i Seveso projekte, projekte više JLS, ocjenu prihvatljivosti, međunarodne i…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal