Property rights and CEOP
A father owns the plot and his son would be the investor in an application under the unified procedure or for location conditions: is their family relationship sufficient?
Answer
Informational English translation. Machine translated; not independently reviewed.
No. The fact that the father is the owner and the son is his relative does not in itself give the son an appropriate right to the land. For the son to be the investor for a building permit, he must himself hold an appropriate right recognised by the Act (e.g. ownership, a lease of publicly owned construction land or another right prescribed by the Act), or another specific legal basis where the Act expressly permits it. Therefore, before submitting the application, the legal basis on which the son is the investor must be established; ordinary family consent must not automatically be treated as a sufficient basis.
Note: For specific infrastructure and other cases the Planning and Construction Act also recognises additional evidence; this rule deliberately does not reduce all situations to the owner's consent.
Original Serbian quotation
„Грађевинска дозвола се издаје инвеститору … који има одговарајуће право на земљишту или објекту”
Informational English translation of the quotation
A building permit is issued to the investor ... who has an appropriate right to the land or structureInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- Do kada se obezbjeđuje izgradnja nedostajuće priključne infrastrukture?Ako je priključenje predviđeno na infrastrukturu koja nije izgrađena, što je utvrđeno LU, uz zahtjev GD podnosi se ugovor…
- Koja postupovna prava čuva član 135 uz zahtjev GD?Stranka je investitor i lice sa na zakonu zasnovanim interesom. GD se izdaje na osnovu važećih LU nezavisno ko ih je tražio.…
- Koji su izričiti izuzeci dokazivanja prava u članu 135?U prvoj fazi podbušivanja podzemne infrastrukture u planiranom koridoru dokazi prava i uklanjanja odlažu se u drugu fazu.…
- How much manoeuvring space must be provided in front of a garage or parking space?There is no single universal figure prescribed by the Law on Planning and Construction for every garage space. For the specific…
- What is checked or submitted with an application in the unified procedure as evidence of the appropriate right to the land?First, the appropriate right held by the investor is determined. The Planning and Construction Act lists ownership, lease of…
- What is a building line?A line on, above and below the surface of land and water up to which construction of the basic footprint of a structure is…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal