Procedures and documentation
Is an application for a decision on the need for assessment submitted for only one phase of the project?
Answer
Informational English translation. Machine translated; not independently reviewed.
No. The application is submitted for the entire project.
Original Serbian quotation
„Zahtev o potrebi procene uticaja podnosi se za ceo projekat”
Informational English translation of the quotation
The application for a decision on the need for impact assessment is submitted for the entire projectInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- Šta sadrži zahtjev za odlučivanje o potrebi EIA i šta se prilaže?Zahtjev za cijeli projekat opisuje nosioca, lokaciju i osjetljivost, cijeli životni ciklus projekta, razumne alternative…
- Koji projekti su izuzeti od primjene EIA zakona?Isključivo suzbijanje neposredne opasnosti po život, zdravlje ili imovinu i spašavanje, samo tokom okolnosti utvrđenih posebnim…
- Must the EIA procedure be completed before the construction permit or other project approval?Yes. When EIA applies, the procedure is carried out before approval for carrying out the project is issued.
- Is there a separate list of projects for which an EIA is mandatory?Yes. The Government prescribes List I of projects for which an impact assessment is mandatory.
- What does the law provide for projects for which a full EIA is not automatic?For List II, an application for a decision on the need for an assessment must be submitted; the competent authority decides by…
- If I have received an opinion in the location conditions, does that complete my EIA obligation?No. The opinion alone does not release the project developer from the obligation to initiate the EIA procedure when the project…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal