CEOP deadlines & fees in Serbia

Interactive overview of statutory deadlines by CEOP phase (location info, location conditions, building permit, Art. 145, work commencement, occupancy permit, cadastre) plus fee obligations and exemptions.

Displays statutory authority deadlines under the Planning and Construction Act and CEOP Rulebook (96/2023, 33/2026). Design and construction duration are additional. Verify current RSD fee amounts in the official Republic Administrative Fees Act and APR CEOP tariff.

1 · Procedure type

2 · Options

Not sure of the building category? Determine it here →

Authority time to start works—
Total statutory time (all steps)—
Utility fees (CEOP Art. 11)—
Legal basis & calculation formula

Legal sources: CEOP Rulebook (Sl. glasnik RS, br. 96/2023, 33/2026) · Planning & Construction Act (72/2009 … 91/2025, 80/2026). Approximate calendar days convert working days using ×1.4 (weekends, excluding public holidays). For current RSD fee amounts, see the Republic Administrative Fees Act and the APR CEOP tariff.

  1. 1

    Location information (optional, pre-design)

    8 days

    Actual issuance cost fee (municipality, notary public or licensed urban planner).

    ZPI, čl. 53
    „Информацију о локацији издаје орган надлежан за издавање локацијских услова у року од осам дана од дана подношења захтева, уз накнаду стварних трошкова издавања те информације.”
    Read full article →
  2. 2

    Obtaining public utility & authority conditions

    15 days (30 days for Art. 133 ZPI)

    FREE for Category A and B buildings. For V and G: authority must notify the fee within 3 working days, otherwise free of charge.

    CEOP pravilnik, čl. 11
    „Imalac javnih ovlašćenja je dužan da uslove iz stava 1. ovog člana, dostavi u roku od 15 dana od dana prijema automatski generisanog zahteva kroz CIS, a za objekte iz člana 133. Zakona u roku od 30 dana od dana prijema automatski generisanog zahteva kroz CIS”
    Read full article →
  3. 3

    Issuance of location conditions after utility responses

    5 working days

    Administrative fee + CEOP fee paid on filing (Art. 6).

    CEOP pravilnik, čl. 13
    „Nadležni organ je dužan da izda lokacijske uslove u skladu sa Zakonom i uredbom koja uređuje izdavanje lokacijskih uslova, u roku od pet radnih dana od dana dostavljanja uslova za projektovanje i priključenje”
    Read full article →
  4. 4

    Building permit issuance

    5 working days

    Administrative fee + CEOP fee. Land development contribution is calculated in the permit and settled before filing notice of works.

    CEOP pravilnik, čl. 19
    „Nadležni organ, ako su ispunjeni uslovi propisani Zakonom i članom 17. ovog pravilnika, donosi rešenje o građevinskoj dozvoli u roku od pet radnih dana od dana podnošenja zahteva.”
    Read full article →
  5. 5

    Notice of commencement of works

    5 working days

    Administrative fee + CEOP fee + third-party liability insurance + proof of settled development contribution (when assessed in permit) + standard power connection contract if provided with LU (CEOP Art. 31, ZPI Art. 148).

    CEOP pravilnik, čl. 31–32
    „Nadležni organ u roku od pet radnih dana potvrđuje prijavu radova”
    Read full article →
  6. 6

    Foundation & structural completion notifications

    Confirmed without delay (forwarded to inspection within 3 days)

    Administrative fee + CEOP fee + geodetic survey of foundations / completed structure (CEOP Arts. 34–36). Inspection reviews foundations within 10 working days.

    CEOP pravilnik, čl. 34–36
    „Izvođač radova podnosi nadležnom organu izjavu o završetku izgradnje objekta u konstruktivnom smislu kroz CIS, odmah po završetku te faze izgradnje.”
    Read full article →
  7. 7

    Utility & infrastructure connection

    15 days

    Connection fee per utility provider final invoice.

    CEOP pravilnik, čl. 42
    „imalac javnih ovlašćenja je dužan da izvrši priključenje objekta na komunalnu i drugu infrastrukturu i da o tome obavesti nadležni organ u roku od 15 dana od dana prijema zahteva za priključenje”
    Read full article →
  8. 8

    Occupancy permit issuance

    5 working days

    Administrative fee + CEOP fee (with technical inspection report and PIO / geodetic survey for Cat. A).

    CEOP pravilnik, čl. 46 i ZPI čl. 158
    „Ako su ispunjeni formalni uslovi iz člana 44. ovog pravilnika, nadležni organ donosi rešenje o upotrebnoj dozvoli u roku od pet radnih dana od dana podnošenja zahteva, u skladu sa Zakonom.”
    Read full article →
  9. 9

    Forwarding to cadastre & ownership registration (ex officio)

    5 working days (forwarding, Art. 49) + 7 days (RGZ entry, Art. 50)

    Authority forwards documents to RGZ within 5 working days of finality (Art. 49); RGZ registers ownership within 7 days (30 days for utility cadastre, Art. 50). Cadastre fee per RGZ decision.

    CEOP pravilnik, čl. 49–50
    „Organ nadležan za poslove državnog premera i katastra, u roku od sedam dana, od dana dostavljanja dokumenata iz člana 49. ovog pravilnika, donosi rešenje kojim vrši upis prava svojine na objektu”
    Read full article →

Key rules on fees, exemptions, validity & appeals

Categories A & B: utility conditions free of charge

For Category A and B buildings, public utility authorities issue design and connection conditions free of charge.

„Uslove za projektovanje i priključenje za objekte kategorije "A" i "B" imalac javnih ovlašćenja izdaje bez naknade.”
CEOP pravilnik, čl. 11 →

No fee notice in 3 working days = free of charge

If an authority fails to notify the fee amount through CIS within 3 working days, the conditions are treated as free of charge.

„kroz CIS obavesti o visini naknade za izdavanje tih uslova, u roku od tri radna dana od prijema automatski generisanog zahteva”
CEOP pravilnik, čl. 11 →

Corrected application within 30 days — no second fee

If an application is rejected for formal defects, you have 30 days to resubmit a corrected filing once without paying administrative and CEOP fees again.

„Ako podnosilac zahteva u roku od 30 dana od dana objavljivanja rešenja iz stava 1. ovog člana, podnese usaglašen zahtev i otkloni sve nedostatke, ne dostavlja dokumentaciju podnetu uz zahtev koji je odbačen, niti ponovo plaća administrativne takse i naknadu”
CEOP pravilnik, čl. 18, 27 i 45 →

Building permit validity: 3 yrs (start) / 5 yrs (occupancy)

A building permit expires if works are not notified within 3 years or occupancy permit is not obtained within 5 years (extendable by 2 years if structurally complete).

„Грађевинска дозвола престаје да важи ако се не изврши пријава радова у року од три године од дана правноснажности решења којим је издата грађевинска дозвола”
ZPI, čl. 140 →

Objection to location conditions: 3 days

An objection against issued location conditions may be filed within 3 days of delivery.

„podnosilac zahteva za izdavanje lokacijskih uslova može izjaviti prigovor nadležnom opštinskom, odnosno gradskom veću, preko nadležnog organa, u roku od tri dana od dana njihovog dostavljanja.”
CEOP pravilnik, čl. 14 →

Appeal: 8 days (permit & Art. 145) / 15 days (demolition)

Appeals on building permits, rejections or Art. 145 decisions must be filed within 8 days (Art. 21), whereas demolition permit appeals have a 15-day deadline (Art. 51a).

„može se preko prvostepenog organa, izjaviti žalba u roku od osam dana od dana dostavljanja”
CEOP pravilnik, čl. 21 i 51a →

Demolition permit appeal: 15 days

Local demolition permit decisions may be appealed within 15 days; Ministry/provincial decisions are challenged via administrative court.

„Na rešenje iz stava 3. ovog člana može se izjaviti žalba u roku od 15 dana od dana dostavljanja rešenja, u skladu sa Zakonom.”
CEOP pravilnik, čl. 51a →

Frequently asked questions

How long does a building permit take in Serbia under CEOP?

Statutory authority deadlines are 5 working days for location conditions directly from a plan (or 15 days for utilities + 5 working days), 5 working days for the building permit, 5 working days for work commencement notice, 5 working days for the occupancy permit, and 7 days for cadastre registration. Design preparation and construction time are additional.

Are utility conditions free for family houses?

Yes. Under Art. 11 of the CEOP Rulebook (96/2023, 33/2026), public utility authorities issue design and connection conditions free of charge for Category A and B buildings.

Do I pay CEOP fees again if my application is rejected?

No, provided you submit a corrected application removing all listed formal defects within 30 days of the rejection decision (one-time right per procedure under CEOP Art. 18, 27 and 45).

How long is a building permit valid?

Under Art. 140 of the Planning and Construction Act, works must be notified within 3 years and an occupancy permit obtained within 5 years of finality (extendable by 2 years if structurally completed).