CEOP deadlines & fees in Serbia
Interactive overview of statutory deadlines by CEOP phase (location info, location conditions, building permit, Art. 145, work commencement, occupancy permit, cadastre) plus fee obligations and exemptions.
Displays statutory authority deadlines under the Planning and Construction Act and CEOP Rulebook (96/2023, 33/2026). Design and construction duration are additional. Verify current RSD fee amounts in the official Republic Administrative Fees Act and APR CEOP tariff.
Frequently asked questions
How long does a building permit take in Serbia under CEOP?
Statutory authority deadlines are 5 working days for location conditions directly from a plan (or 15 days for utilities + 5 working days), 5 working days for the building permit, 5 working days for work commencement notice, 5 working days for the occupancy permit, and 7 days for cadastre registration. Design preparation and construction time are additional.
Are utility conditions free for family houses?
Yes. Under Art. 11 of the CEOP Rulebook (96/2023, 33/2026), public utility authorities issue design and connection conditions free of charge for Category A and B buildings.
Do I pay CEOP fees again if my application is rejected?
No, provided you submit a corrected application removing all listed formal defects within 30 days of the rejection decision (one-time right per procedure under CEOP Art. 18, 27 and 45).
How long is a building permit valid?
Under Art. 140 of the Planning and Construction Act, works must be notified within 3 years and an occupancy permit obtained within 5 years of finality (extendable by 2 years if structurally completed).