Procedures and documentation
How is completion of the structural phase of a structure reported?
Answer
Informational English translation. Machine translated; not independently reviewed.
Immediately after completion of the structural phase, the contractor submits a statement through CIS, with a geodetic survey of the structure and proof of payment of fees and the CEOP charge. The authority confirms receipt without delay or orders a proper notification or proof in the prescribed case.
Original Serbian quotation
„Извођач радова подноси надлежном органу изјаву о завршетку изградње објекта у конструктивном смислу кроз ЦИС, одмах по завршетку те фазе изградње.
Надлежни орган без одлагања потврђује пријем изјаве из става 1. овог члана, осим ако је подносилац у пријави навео податке који нису у складу са подацима из грађевинске дозволе, односно решења из члана 145. Закона на основу којих се гради, као и ако није доставио доказ о уплати административних такси и накнаде за Централну евиденцију, у ком случају налаже инвеститору да без одлагања достави уредну пријаву завршетка изградње објекта у конструктивном смислу, односно доказ о уплати административних такси и накнаде за Централну евиденцију и обавештава га да ће се ако не поступи по том налогу сматрати да није извршена уредна пријава завршетка изградње објекта у конструктивном смислу.
Извођач радова уз изјаву о завршетку изградње објекта у конструктивном смислу подноси геодетски снимак објекта, као и доказ о уплати административних такси и накнаде за Централну евиденцију.
Надлежни орган, у року од три дана од дана пријема изјаве из става 1. овог члана, обавештава надлежну грађевинску инспекцију о пријему те изјаве, без обзира да ли је та изјава уредна и потпуна.
Ако надлежни орган на основу геодетског снимка утврди да постоји одступање геодетског снимка у односу на издату грађевинску дозволу, без одлагања ће о томе обавестити грађевинског инспектора.
Надлежна грађевинска инспекција је обавезна да у року од десет радних дана по пријему обавештења из става 4. овог члана изврши инспекцијски надзор изграђеног објекта у складу са Законом и да о резултатима тог надзора обавести надлежни орган.
9. Достављање техничке документације
Подношење захтева за давање сагласности на техничку документацију у погледу мера заштите од пожара”
Informational English translation of the quotation
The contractor shall submit to the competent authority a statement of completion of construction of the structure in structural terms through CIS, immediately after completion of that construction phase.
The competent authority shall confirm receipt of the statement referred to in paragraph 1 of this Article without delay, unless the applicant has entered information in the notification that is inconsistent with the construction permit or the decision under Article 145 of the Law on the basis of which construction is carried out, or has not submitted proof of payment of administrative fees and the Central Register charge, in which case it shall order the investor to submit without delay a proper notification of completion of construction of the structure in structural terms or proof of payment of administrative fees and the Central Register charge, and shall inform the investor that failure to comply with that order will mean that proper notification of completion of construction of the structure in structural terms is deemed not to have been made.
The contractor shall submit, with the statement of completion of construction of the structure in structural terms, a geodetic survey of the structure and proof of payment of administrative fees and the Central Register charge.
Within three days of receipt of the statement referred to in paragraph 1 of this Article, the competent authority shall notify the competent construction inspectorate of its receipt, regardless of whether the statement is proper and complete.
If the competent authority determines from the geodetic survey that the survey differs from the issued construction permit, it shall notify the construction inspector without delay.
The competent construction inspectorate must, within ten working days of receipt of the notification referred to in paragraph 4 of this Article, inspect the constructed structure in accordance with the Law and inform the competent authority of the results of that inspection.
9. Submission of technical documentation
Submission of an application for approval of technical documentation regarding fire protection measuresInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- Koji rokovi važe za obavještavanje i nadzor završene konstrukcije?Organ obavještava inspekciju u tri dana od prijema izjave i kada nije uredna/potpuna; o odstupanju geodetskog snimka od GD…
- If technical documentation is submitted in DWF/DWFX/DWG, must a PDF also be provided?Yes. DWF/DWFX/DWG is permitted in prescribed cases, but a copy in PDF format, appropriately electronically signed, must also be…
- Is a CEOP application submitted and signed through CIS?Yes. The relevant application is completed through CIS and signed with the qualified electronic signature of the applicant or…
- In what format is a site plan submitted to CEOP?The site plan must also be submitted in DWG or DXF format, georeferenced in the national coordinate system, together with the…
- What must be attached when a CEOP application is submitted through an authorised representative?A power of attorney in electronic PDF form with a qualified electronic signature, or a properly digitised power of attorney…
- How many times can I exercise the right to submit a compliant application without paying the administrative fee again and without resubmitting documentation already submitted?The benefit of a compliant application without resubmitting documentation and fees and charges already paid may be used only…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal