Procedures and documentation
What additional documents are submitted for connection to the electricity distribution system?
Answer
Informational English translation. Machine translated; not independently reviewed.
In addition to Article 40: for voltage up to 1 kV, an occupancy permit or a contractor’s statement with confirmation by the responsible contractor that the work was properly executed and a report on the soundness of the installation is submitted; above 1 kV an occupancy permit is mandatory. Supply contract details are submitted. If the supply is not full supply, details of balancing responsibility with the transmission operator and system access with the distribution operator are also submitted. For a transformer station/line required for a connection above 1 kV, other evidence specified in the location conditions is also submitted.
Note: The alternative of a statement/report must not be extended to structures above 1 kV. The official source in paragraph 2 says “paragraph 2 item 2” instead of the expected paragraph 1; do not amend the quotation.
Original Serbian quotation
„Уз захтев за прикључење oбјекта на дистрибутивни систем електричне енергије, поред прилога из члана 40. овог правилника, прилаже се и:
1) употребна дозвола или изјава извођача радова, са потврдом одговорног извођача радова да су уређаји и инсталације изведени у складу са прописима и стандардима који важи за поједине врсте радова, инсталација и опреме и извештајем о исправности те инсталације, коју је извођач радова сачинио у складу са актом којим се уређују технички услови за електричне инсталације ниског напона, за објекте који се прикључује на напонски ниво до 1 kV, односно употребна дозвола за објекат који се прикључује на напонски ниво изнад 1 kV;
2) информација о броју и датуму закључења уговора о снабдевању, врсти уговора, периоду снабдевања, снабдевачу и крајњем купцу.
У случају да са крајњим купцем није закључен уговор о потпуном снабдевању, подносилац захтева поред информације из става 2. тачка 2) овог члана прилаже и:
1) информацију о броју и датуму закључења уговора којим је уређена балансна одговорност са оператором преносног система електричне енергије и
2) информацију о броју и датуму закључења уговора којим је уређен приступ систему са оператором дистрибутивног система електричне енергије.
Ако је за прикључење објекта на напонски ниво изнад 1 kV потребно прикључење трансформаторске станице и/или подземног или надземног вода, достављају се и други докази наведени у условима за пројектовање и прикључење, који су прибављени у поступку издавања локацијских услова.
Поступање ималаца јавних овлашћења”
Informational English translation of the quotation
In addition to the attachments under Article 40 of this Rulebook, an application for connection of a structure to the electricity distribution system shall also be accompanied by:
1) an occupancy permit or a contractor’s statement, with confirmation by the responsible contractor that the devices and installations have been executed in accordance with the regulations and standards applicable to particular types of work, installations and equipment, and a report on the soundness of that installation, prepared by the contractor in accordance with the act regulating technical requirements for low-voltage electrical installations, for structures connected at a voltage level up to 1 kV, or an occupancy permit for a structure connected at a voltage level above 1 kV;
2) information on the number and date of conclusion of the supply contract, type of contract, supply period, supplier and final customer.
If a full supply contract has not been concluded with the final customer, the applicant shall, in addition to the information under paragraph 2 item 2) of this Article, also attach:
1) information on the number and date of conclusion of the contract governing balancing responsibility with the electricity transmission system operator and
2) information on the number and date of conclusion of the contract governing system access with the electricity distribution system operator.
If connection of a transformer station and/or underground or overhead line is required to connect a structure at a voltage level above 1 kV, other evidence listed in the design and connection conditions obtained in the procedure for issuing location conditions shall also be submitted.
Action by holders of public authorityInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- If technical documentation is submitted in DWF/DWFX/DWG, must a PDF also be provided?Yes. DWF/DWFX/DWG is permitted in prescribed cases, but a copy in PDF format, appropriately electronically signed, must also be…
- Is a CEOP application submitted and signed through CIS?Yes. The relevant application is completed through CIS and signed with the qualified electronic signature of the applicant or…
- In what format is a site plan submitted to CEOP?The site plan must also be submitted in DWG or DXF format, georeferenced in the national coordinate system, together with the…
- What must be attached when a CEOP application is submitted through an authorised representative?A power of attorney in electronic PDF form with a qualified electronic signature, or a properly digitised power of attorney…
- How many times can I exercise the right to submit a compliant application without paying the administrative fee again and without resubmitting documentation already submitted?The benefit of a compliant application without resubmitting documentation and fees and charges already paid may be used only…
- Kako se izdaje klauzula pravnosnažnosti i ispravlja greška akta?Donosilac po službenoj dužnosti ili zahtjevu stranke izdaje klauzulu pravnosnažnosti kao propisno elektronski sastavljenu…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal