What is the deadline for issuing location conditions if they can be determined from the planning document?
Answer
Informational English translation. Machine translated; not independently reviewed.
If location conditions can be determined by consulting the plan or separate conditions document (separat), they are issued within five working days of receipt of the application. Within the same period they may be issued on the basis of the planning document and a confirmed urban planning project (UP).
Original Serbian quotation
„Ако се локацијски услови могу утврдити увидом у плански документ, односно сепарат, надлежни орган је дужан да их изда у року од пет радних дана од дана пријема захтева из члана 6. овог правилника, у складу са Законом и уредбом која уређује издавање локацијских услова, и да о томе обавести подносиоца захтева.
Локацијски услови се могу издати и на основу планског документа и потврђеног урбанистичког пројекта у року из става 1. овог члана.
Изузетно од члана 9. овог правилника, ако надлежни орган увидом у плански документ, односно сепарат утврди да захтев није у складу са тим документом, односно сепаратом, неће прибављати документацију од органа надлежног за послове државног премера и катастра, већ ће издати локацијске услове у којима ће констатовати да није могуће дозволити градњу у складу са поднетим захтевом, уз навођење забрана и ограничења садржаних у планском документу, односно сепарату.
Издавање локацијских услова прибављањем услова за пројектовање и прикључење од имаоца јавних овлашћења”
Informational English translation of the quotation
If location conditions can be determined by consulting the planning document or separate conditions document (separat), the competent authority must issue them within five working days from receipt of the application under Article 6 of this Rulebook, in accordance with the Law and the Regulation governing issuance of location conditions, and notify the applicant thereof.
Location conditions may also be issued on the basis of the planning document and a confirmed urban planning project within the period referred to in paragraph 1 of this Article.
As an exception to Article 9 of this Rulebook, if the competent authority, by consulting the planning document or separate conditions document (separat), determines that the application does not comply with that document or separate conditions document, it shall not obtain documentation from the authority responsible for state survey and cadastre, but shall issue location conditions stating that construction cannot be permitted in accordance with the submitted application, specifying the prohibitions and restrictions contained in the planning document or separate conditions document.
Issuance of location conditions by obtaining design and connection conditions from holders of public powersInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- What is done if the application does not comply with the planning document?The authority issues location conditions stating that construction cannot be permitted, specifying the prohibitions and…
- If technical documentation is submitted in DWF/DWFX/DWG, must a PDF also be provided?Yes. DWF/DWFX/DWG is permitted in prescribed cases, but a copy in PDF format, appropriately electronically signed, must also be…
- Is a CEOP application submitted and signed through CIS?Yes. The relevant application is completed through CIS and signed with the qualified electronic signature of the applicant or…
- In what format is a site plan submitted to CEOP?The site plan must also be submitted in DWG or DXF format, georeferenced in the national coordinate system, together with the…
- What must be attached when a CEOP application is submitted through an authorised representative?A power of attorney in electronic PDF form with a qualified electronic signature, or a properly digitised power of attorney…
- How many times can I exercise the right to submit a compliant application without paying the administrative fee again and without resubmitting documentation already submitted?The benefit of a compliant application without resubmitting documentation and fees and charges already paid may be used only…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal