Procedures and documentation
Within what time must a holder of public powers make the connection?
Answer
Informational English translation. Machine translated; not independently reviewed.
The general deadline is 15 days from receipt of the application if construction followed the construction permit/design for execution (PZI) and additional location condition requirements are met, with notice to the authority and a final invoice. If the amount was not included in the conditions, connection takes place within that period regardless of calculation/payment. If the investor chose payment after the final calculation, the 15 days start on the day after proof of payment is submitted through CIS. For electricity the connection deadline cannot fall before the agreed deadline for completion of the connection works. Mandatory verification takes place in the same procedure and period; unmet conditions are reported with all deficiencies.
Original Serbian quotation
„Ако је објекат изведен у складу са грађевинском дозволом и пројектом за извођење, ималац јавних овлашћења је дужан да изврши прикључење објекта на комуналну и другу инфраструктуру и да о томе обавести надлежни орган у року од 15 дана од дана пријема захтева за прикључење, уз доставу фактуре у складу са коначним обрачуном накнаде за прикључење објекта на одговарајућу инфраструктуру. Ако је локацијским условима предвиђено испуњење додатних услова за прикључење тог објекта на инфраструктуру, прикључење ће се извршити ако су испуњени ти услови.
Ако износ накнаде за прикључење објекта на инфраструктуру није наведен у условима за пројектовање и прикључење тог објекта, ималац јавних овлашћења прикључује објект на инфраструктуру у року из става 1. овог члана, без обзира да ли је коначан обрачун накнаде за прикључење објекта у међувремену достављен инвеститору и да ли је плаћање по том обрачуну извршено.
Изузетно од става 1. овог члана, ако је инвеститор у захтеву навео да ће плаћање накнаде извршити тек након што му се достави коначан обрачун накнаде за прикључење објекта на одговарајућу инфраструктуру, рок од 15 дана из става 1. овог члана почиње да тече наредног дана од достављања доказа о уплати те накнаде кроз ЦИС.
Ако ималац јавних овлашћења има законску обавезу провере испуњености услова за прикључење објекта на комуналну, односно другу инфраструктуру, он ту проверу врши у поступку прикључења, поступајући по захтеву из члана 40. став 1. овог правилника, у оквиру рокова прописаних овим чланом.
Изузетно од става 1. овог члана, у случају прикључења објекта на дистрибутивни систем електричне енергије, рок за прикључење не може наступити пре истека рока за завршетак радова на изградњи прикључка, који се уговара у складу са прописом који уређује услове испоруке и снабдевања електричном енергијом.
Ако нису испуњени услови за прикључење објекта на инфраструктуру, ималац јавних овлашћења ће о томе обавестити надлежни орган уз навођење свих недостатака услед којих прикључење није могуће извршити.
11. Издавање употребне дозволе
Подношење захтева за издавање употребне дозволе”
Informational English translation of the quotation
If the structure has been constructed in accordance with the construction permit and design for execution, the holder of public powers must connect the structure to utility and other infrastructure and notify the competent authority thereof within 15 days from receipt of the connection application, delivering an invoice in accordance with the final calculation of the fee for connecting the structure to the relevant infrastructure. If the location conditions provide for additional conditions for connection of that structure to infrastructure, connection shall be made if those conditions are met.
If the amount of the fee for connecting the structure to infrastructure is not stated in the design and connection conditions for that structure, the holder of public powers shall connect the structure to infrastructure within the period under paragraph 1 of this Article, regardless of whether the final calculation of the connection fee has meanwhile been delivered to the investor and whether payment under that calculation has been made.
As an exception to paragraph 1 of this Article, if the investor stated in the application that the fee would be paid only after delivery of the final calculation of the fee for connecting the structure to the relevant infrastructure, the 15-day period under paragraph 1 of this Article begins on the day following submission of proof of payment of that fee through CIS.
If the holder of public powers has a statutory obligation to verify compliance with the conditions for connecting the structure to utility or other infrastructure, it shall carry out that verification in the connection procedure, acting on the application under Article 40 paragraph 1 of this Rulebook, within the deadlines prescribed by this Article.
As an exception to paragraph 1 of this Article, in the case of connection of a structure to the electricity distribution system, the connection deadline cannot fall before expiry of the deadline for completion of the connection construction works, agreed in accordance with the regulation governing electricity delivery and supply conditions.
If the conditions for connection of the structure to infrastructure are not met, the holder of public powers shall notify the competent authority, specifying all deficiencies preventing connection.
11. Issuance of an occupancy permit
Submission of an application for an occupancy permitInformational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- If technical documentation is submitted in DWF/DWFX/DWG, must a PDF also be provided?Yes. DWF/DWFX/DWG is permitted in prescribed cases, but a copy in PDF format, appropriately electronically signed, must also be…
- Is a CEOP application submitted and signed through CIS?Yes. The relevant application is completed through CIS and signed with the qualified electronic signature of the applicant or…
- In what format is a site plan submitted to CEOP?The site plan must also be submitted in DWG or DXF format, georeferenced in the national coordinate system, together with the…
- What must be attached when a CEOP application is submitted through an authorised representative?A power of attorney in electronic PDF form with a qualified electronic signature, or a properly digitised power of attorney…
- How many times can I exercise the right to submit a compliant application without paying the administrative fee again and without resubmitting documentation already submitted?The benefit of a compliant application without resubmitting documentation and fees and charges already paid may be used only…
- Kako se izdaje klauzula pravnosnažnosti i ispravlja greška akta?Donosilac po službenoj dužnosti ili zahtjevu stranke izdaje klauzulu pravnosnažnosti kao propisno elektronski sastavljenu…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal