Procedures and documentation
What must be attached to an application to amend a construction permit?
Answer
Informational English translation. Machine translated; not independently reviewed.
The application is submitted through CIS. Attachments depend on the reason for amendment: 1) if the PGD changes: a new PGD or a separate design section containing amendments, with an extract and the statement under Article 16 paragraph 2 item 3; 2) if the investor changes: evidence of acquisition or loss of the appropriate right, subject to statutory exceptions, with evidence of tax payment or that the transaction is not taxable; 3) if a financier is added: the contract between the investor and financier, and for removal of the financier, their consent; 4) if the method of paying the contribution changes: the investor's statement on that method; 5) an updated environmental impact assessment study and approval, or a decision that updating is unnecessary, with a statement by the investor and responsible designer that the documentation complies with environmental protection measures and conditions; 6) if the PGD changes: a decision approving the construction and demolition waste management plan. If the amendments do not comply with the energy permit for a particular type of structure, or the location changes and/or the installed capacity of the energy structure increases, the authority instructs the applicant to obtain a new energy permit.
Note: The list in Article 22 must be read with every condition and statutory exception; it is not a list of unconditionally mandatory attachments for every structure. The waste plan and impact assessment apply within the scope of their respective special regulations. This rule does not replace examination of the specific application.
Original Serbian quotation
„Postupak za izmenu rešenja o građevinskoj dozvoli sprovodi se u objedinjenoj proceduri, a pokreće se podnošenjem zahteva nadležnom organu kroz CIS.
Uz zahtev za izmenu rešenja o građevinskoj dozvoli dostavlja se:
1) novi projekat za građevinsku dozvolu, odnosno separat izmena projekta za građevinsku dozvolu, sa izvodom iz projekta za građevinsku dozvolu, izrađen u skladu sa pravilnikom kojim se uređuje sadržina tehničke dokumentacije dokumentacije i izjavom iz člana 16. stav 2. tačka 3) ovog pravilnika, ako se izmena traži zbog izmene projekta za građevinsku dozvolu;
2) dokaz o sticanju, odnosno gubitku odgovarajućeg prava na zemljištu ili objektu u smislu Zakona, osim ako je to pravo upisano u javnoj knjizi ili je uspostavljeno zakonom, odnosno ako je Zakonom propisano da se taj dokaz ne dostavlja, ako se izmena traži zbog promene investitora, sa dokazom o plaćenom odgovarajućem porezu u skladu sa zakonom kojim se uređuju porezi na imovinu, odnosno dokazom da promet građevinskog zemljišta, odnosno objekta u izgradnji nije predmet oporezivanja u skladu sa zakonom kojim se uređuju porezi na imovinu;
3) ugovor između investitora i finansijera, ako se izmena traži zbog unosa finansijera u rešenje, odnosno saglasnost finansijera za njegovo brisanje iz rešenja o građevinskoj dozvoli, ako se izmena traži zbog brisanja finansijera iz tog rešenja;
4) izjašnjenje investitora o načinu plaćanja doprinosa za uređivanje građevinskog zemljišta, ako se izmena traži zbog promene načina plaćanja doprinosa;
5) ažurirana studija o proceni uticaja na životnu sredinu, saglasnost na ažuriranu studiju o proceni uticaja na životnu sredinu, odnosno odluka da nije potrebno ažuriranje studije o proceni uticaja projekta na životnu sredinu uz izjavu investitora i odgovornog projektanta, kojom potvrđuju da je priložena dokumentacija usaglašena sa merama i uslovima zaštite životne sredine;
6) rešenje o saglasnosti na plan upravljanja otpadom od građenja i rušenja, ako se izmena traži zbog izmene projekta za građevinsku dozvolu.
U slučaju da izmene iz ovog člana nisu u skladu sa izdatom energetskom dozvolom za posebnu vrstu objekata, odnosno da se menjaju podaci o lokaciji i/ili se povećava instalisana snaga energetskog objekta, nadležni organ upućuje podnosioca zahteva da je potrebno da pribavi novu energetsku dozvolu.”
Informational English translation of the quotation
The procedure for amending a construction permit decision is conducted under the unified procedure and is initiated by submitting an application to the competent authority through CIS.
The following shall be submitted with the application to amend the construction permit decision:
1) a new design for a construction permit, or a separate design section containing amendments to the design for a construction permit, with an extract from the design for a construction permit, prepared in accordance with the Rulebook governing the contents of technical documentation documentation, and the statement under Article 16 paragraph 2 item 3) of this Rulebook, if the amendment is requested because the design for a construction permit has changed;
2) evidence of acquisition or loss of the appropriate right to the land or structure within the meaning of the Law, unless that right is entered in a public register or established by law, or the Law provides that such evidence is not submitted, if the amendment is requested because of a change of investor, with evidence of payment of the relevant tax under the law governing property taxes, or evidence that the transfer of construction land or a structure under construction is not subject to taxation under the law governing property taxes;
3) the contract between the investor and financier, if the amendment is requested to add the financier to the decision, or the financier's consent to removal from the construction permit decision, if the amendment is requested to remove the financier from that decision;
4) the investor's statement on the method of payment of the contribution for the development of construction land, if the amendment is requested because of a change in the method of paying the contribution;
5) an updated environmental impact assessment study, approval of the updated environmental impact assessment study, or a decision that updating the project's environmental impact assessment study is not required, together with a statement by the investor and responsible designer confirming that the attached documentation complies with environmental protection measures and conditions;
6) a decision approving the construction and demolition waste management plan, if the amendment is requested because of a change to the design for a construction permit.
If the amendments under this Article do not comply with the issued energy permit for a particular type of structure, or the location details change and/or the installed capacity of the energy structure increases, the competent authority instructs the applicant that a new energy permit must be obtained.Informational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- If technical documentation is submitted in DWF/DWFX/DWG, must a PDF also be provided?Yes. DWF/DWFX/DWG is permitted in prescribed cases, but a copy in PDF format, appropriately electronically signed, must also be…
- Is a CEOP application submitted and signed through CIS?Yes. The relevant application is completed through CIS and signed with the qualified electronic signature of the applicant or…
- In what format is a site plan submitted to CEOP?The site plan must also be submitted in DWG or DXF format, georeferenced in the national coordinate system, together with the…
- What must be attached when a CEOP application is submitted through an authorised representative?A power of attorney in electronic PDF form with a qualified electronic signature, or a properly digitised power of attorney…
- How many times can I exercise the right to submit a compliant application without paying the administrative fee again and without resubmitting documentation already submitted?The benefit of a compliant application without resubmitting documentation and fees and charges already paid may be used only…
- Kako se izdaje klauzula pravnosnažnosti i ispravlja greška akta?Donosilac po službenoj dužnosti ili zahtjevu stranke izdaje klauzulu pravnosnažnosti kao propisno elektronski sastavljenu…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal