The application is submitted through CIS. Article 43 lists: 1) the as-built design or the PZI with a statement by the investor, professional supervisor and responsible contractor that there are no deviations and that the as-built state equals the designed state; 2) for structures under Article 145 without a mandatory PZI: the IDP with an appropriate statement by the same participants; 3) the technical inspection commission report on fitness for use with a proposal to issue the permit; 4) a specification of separate parts with name/designation, floor, layout and net area, if any; 5) the house number decision, if prescribed; 6) proof of fees and the Central Register fee; 7) the energy certificate issued through CREP, if prescribed; 8) a digital geodetic works technical report for the structure and separate parts with a digital geodetic field record in xml format; 9) a technical report on as-built installations and infrastructure structures with digital parts in txt/xls and dwg/dxf format; 10) the waste movement document or hazardous waste movement document confirming delivery of construction waste to a treatment or storage operator. For cases under a special law allowing foreign regulations/standards and recognised methods, a separate technical report on fitness for use is also submitted as required by that paragraph. If the statement on completion of foundations and/or the structure is missing, a subsequent report by a geodetic expert on the foundations or by the competent inspector on the structure is accepted in accordance with the Law. Approvals of documentation obtained outside the unified procedure where prescribed, and proof of subdivision/re-parcelling or a change of plot number if carried out by the application, are also attached. A certificate of payment of the fee for use of publicly owned land may be attached for information; this paragraph does not make it mandatory. The investor may also request an occupancy permit for works under a decision pursuant to Article 145.

Note: The list in Article 43 must be read with each condition and statutory exception; it is not a list of attachments unconditionally required for every structure. The waste plan and impact assessment apply within the scope of their respective special regulations. This rule does not replace checking the individual application.

Original Serbian quotation

„Postupak za izdavanje upotrebne dozvole pokreće se podnošenjem zahteva nadležnom organu kroz CIS. Uz zahtev iz stava 1. ovog člana prilaže se: 1) projekat izvedenog objekta, izrađen u skladu sa pravilnikom kojim se uređuje sadržina tehničke dokumentacije, odnosno projekat za izvođenje sa izjavom investitora, vršioca stručnog nadzora i odgovornog izvođača radova, kojom se potvrđuje da nije odstupljeno od projekta za izvođenje i da je izvedeno stanje jednako projektovanom stanju. Izjava se sačinjava u skladu sa pravilnikom kojim se uređuje sadržina, način i postupak izrade i način vršenja kontrole tehničke dokumentacije prema klasi i nameni objekata; 2) idejni projekat sa izjavom investitora, vršioca stručnog nadzora i odgovornog izvođača radova da nije odstupljeno od idejnog projekta i da je izvedeno stanje jednako projektovanom stanju, za objekte iz člana 145. Zakona za koje nije propisana izrada projekta za izvođenje. Izjava se sačinjava u skladu sa pravilnikom kojim se uređuje sadržina, način i postupak izrade i način vršenja kontrole tehničke dokumentacije prema klasi i nameni objekata; 3) izveštaj komisije za tehnički pregled, kojim se utvrđuje da je objekat podoban za upotrebu, sa predlogom za izdavanje upotrebne dozvole; 4) specifikacija posebnih delova objekta, ako objekat ima posebne delove (koja sadrži njihovo označenje - naziv i oznaku, sprat, strukturu i neto površinu); 5) rešenje o utvrđivanju kućnog broja, ako je za objekat propisana obaveza utvrđivanja kućnog broja; 6) dokaz o uplati administrativne takse za podnošenje zahteva i donošenje rešenja kojim se dozvoljava upotreba izvedenih radova, kao i dokaz o uplati naknade za Centralnu evidenciju; 7) sertifikat o energetskim svojstvima objekta, ako je za objekat propisana obaveza pribavljanja tog sertifikata, izdat kroz centralni registar energetskih pasoša (CREP); 8) digitalni elaborat geodetskih radova za izvedeni objekat i posebne delove objekta sa obavezno dostavljenim digitalnim geodetskim manualom u xml formatu; 9) elaborat geodetskih radova za izvedene instalacije i infrastrukturne objekte sa digitalnim delovima elaborata u txt/xls i dwg/dxf formatu; 10) dokument o kretanju otpada, odnosno dokument o kretanju opasnog otpada kojim se potvrđuje da je otpad nastao građenjem i rušenjem (građevinski otpad), predat operateru postrojenja za tretman, odnosno skladištenje otpada. Uz zahtev za izdavanje upotrebne dozvole za objekte za koje je posebnim zakonom propisano da se prilikom ocene ispunjenosti osnovnih zahteva za objekat, kao i zahteva za projektovanje, izvođenje i održavanje objekta koriste inostrani propisi i standardi i priznate metode proračuna i modela, ukoliko su tim propisima predviđeni, uz izveštaj komisije za tehnički pregled iz stava 5. ovog člana, dostavlja se i poseban elaborat kojim se dokazuje da je objekat podoban za upotrebu na osnovu inostranih propisa i standarda i priznatih metoda proračuna i modela. Ako se u postupku izdavanja upotrebne dozvole utvrdi da nedostaje izjava o završetku izgradnje temelja i/ili završetku izgradnje objekta u konstruktivnom smislu, urednom dokumentacijom, smatra se i naknadno dostavljeni izveštaj veštaka geodetske struke da su temelji postavljeni i urađeni u skladu sa izdatom građevinskom dozvolom, odnosno izveštaj nadležnog građevinskog inspektora da je objekat završen u konstruktivnom smislu, u skladu sa Zakonom. Uz zahtev za izdavanje upotrebne dozvole, za objekte za koje je posebnim propisima predviđeno pribavljanje saglasnosti na tehničku dokumentaciju izvan objedinjene procedure, investitor dostavlja i saglasnost nadležnog organa, odnosno posebne organizacije. Podnosilac može uz zahtev iz stava 1. ovog člana priložiti i potvrdu o izmirenju obaveze po osnovu naknade za upotrebu zemljišta u javnoj svojini (zemljište u putnom i železničkom pojasu i sl.), u cilju informisanja o izvršenom plaćanju, nadležnog organa, odnosno imaoca javnih ovlašćenja koji učestvuje u objedinjenoj proceduri. Ako je do podnošenja zahteva u katastru sprovedena parcelacija, odnosno preparcelacija u skladu sa izdatim lokacijskim uslovima ili je promenjen broj parcele, odnosno parcela za koje su izdati lokacijski uslovi odnosno građevinska dozvola, uz zahtev se prilaže i dokaz o toj promeni (rešenje, odnosno uverenje organa nadležnog za poslove državnog premera i katastra o izvršenoj parcelaciji, odnosno preparcelaciji, odnosno promeni broja parcele, odnosno parcela). Investitor može podneti zahtev za izdavanje upotrebne dozvole i za radove izvedene u skladu sa rešenjem iz člana 145. Zakona.”
Informational English translation of the quotation
The procedure for issuing an occupancy permit is initiated by submitting an application to the competent authority through CIS. The following must be attached to the application referred to in paragraph 1 of this Article: 1) the as-built design, prepared in accordance with the Rulebook governing the content of technical documentation, or the design for execution (PZI) with a statement by the investor, professional supervisor and responsible contractor confirming that there was no departure from the design for execution and that the as-built state equals the designed state. The statement is prepared in accordance with the Rulebook governing the content, method and procedure for preparation and method of checking technical documentation according to the class and intended use of structures; 2) the preliminary design with a statement by the investor, professional supervisor and responsible contractor that there was no departure from the preliminary design and that the as-built state equals the designed state, for structures under Article 145 of the Law for which preparation of a design for execution is not prescribed. The statement is prepared in accordance with the Rulebook governing the content, method and procedure for preparation and method of checking technical documentation according to the class and intended use of structures; 3) the technical inspection commission report establishing that the structure is fit for use, with a proposal to issue an occupancy permit; 4) a specification of separate parts of the structure, if the structure has separate parts (containing their identification - name and designation, floor, layout and net area); 5) the decision assigning a house number, if assignment of a house number is mandatory for the structure; 6) proof of payment of the administrative fee for submitting the application and issuing the decision permitting use of the completed works, and proof of payment of the Central Register fee; 7) the energy performance certificate for the structure, if obtaining that certificate is mandatory for the structure, issued through the central register of energy passports (CREP); 8) a digital geodetic works technical report for the completed structure and its separate parts, with a digital geodetic field record in xml format, which must be submitted; 9) a geodetic works technical report for the completed installations and infrastructure structures, with digital parts of the report in txt/xls and dwg/dxf format; 10) a waste movement document or hazardous waste movement document confirming that waste generated by construction and demolition (construction waste) has been delivered to the operator of a waste treatment or storage facility. With an application for an occupancy permit for structures for which a special law prescribes the use of foreign regulations and standards and recognised calculation methods and models, if provided for by those regulations, when assessing compliance with the basic requirements for the structure and requirements for its design, execution and maintenance, a separate technical report proving that the structure is fit for use on the basis of foreign regulations and standards and recognised calculation methods and models must also be submitted with the technical inspection commission report referred to in paragraph 5 of this Article. If, during the occupancy permit procedure, it is established that a statement on completion of construction of the foundations and/or completion of the structure in the structural sense is missing, documentation in proper order also includes a subsequently submitted report by a geodetic expert that the foundations have been set out and built in accordance with the issued construction permit, or a report by the competent construction inspector that the structure has been completed in the structural sense, in accordance with the Law. With an application for an occupancy permit for structures for which special regulations provide for obtaining approval of technical documentation outside the unified procedure, the investor must also submit the approval of the competent authority or special organisation. The applicant may also attach to the application referred to in paragraph 1 of this Article a certificate that the obligation to pay the fee for use of publicly owned land (land within a road or railway corridor and the like) has been settled, in order to inform the competent authority or holder of public authority participating in the unified procedure of the payment made. If, by the time the application is submitted, subdivision or re-parcelling has been carried out in the cadastre in accordance with the issued location conditions, or the number of the plot or plots for which the location conditions or construction permit were issued has changed, proof of that change must also be attached to the application (a decision or certificate of the authority responsible for state survey and cadastre confirming the subdivision, re-parcelling or change of the number of the plot or plots). The investor may also submit an application for an occupancy permit for works carried out in accordance with a decision under Article 145 of the Law.

Official source ↗

Regulation
Pravilnik o sprovođenju objedinjene procedure (CEOP)
Article
Art. 43
Official gazette
Sl. glasnik RS, br. 96/2023 i 33/2026
Topic
Procedures and documentation

Informational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.

Explore related rules →

Related questions

Search building rules

The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal

SEARCH
Select Language