The basic period is five years from the date the construction permit decision or its amended decision becomes final. Structures under Article 133, utility infrastructure constructed in phases, publicly owned public-purpose structures and family residential buildings for the investor's own housing needs are excepted. In proceedings initiated in time, the authority may extend validity by two years if structural completion is established by an inspector's record. Independent transitional provisions must be applied separately, including Article 41 of the 91/2025 amendments on an additional period for issuing an occupancy permit.
Note: Exceeding one entered figure does not automatically prove that the construction permit has ceased to be valid; exceptions, finality or amendment, the separate decision and the transitional regime must first be established.
Original Serbian quotation
„Грађевинска дозвола престаје да важи ако се не изврши пријава радова у року од три године од дана правноснажности решења којим је издата грађевинска дозвола , односно не изврши пријава радова у року од три године од дана правноснажности решења о измени решења о грађевинској дозволи.
Изузетно од става 1. овог члана, када је пријава радова извршена на основу члана 148. став 6. овог закона, грађевинска дозвола важи до пријаве радова свих делова објекта.
Решење којим се утврђује престанак важења грађевинске дозволе из ст. 1. и 2. овог члана доноси орган надлежан за издавање грађевинске дозволе.
Грађевинска дозвола престаје да важи ако се у року од пет година од дана правноснажности решења којим је издата грађевинска дозвола, односно правноснажности решења о измени решења о грађевинској дозволи, не изда употребна дозвола, осим за објекте из члана 133. овог закона, објекте комуналне инфраструктуре који се изводе фазно, објекте јавне намене у јавној својини и породичне стамбене зграде које инвеститор гради ради решавања својих стамбених потреба .
На захтев инвеститора, надлежни орган може донети решење којим се одобрава да правноснажна грађевинска дозвола остаје на правној снази две године после рока прописаног ставом 4. овог члана, ако се у поступку покренутом у року из ставa 4. овог члана, утврди да је објекат завршен у конструктивном смислу на основу записника надлежног грађевинског инспектора.
После истека рока из става 4. овог члана, инвеститор плаћа на рачун Пореске управе накнаду у висини пореза на имовину, који би се плаћао у складу са законом којим се уређује порез на имовину за цео објекат, да је исти изграђен у складу са грађевинском дозволом, све док се за ту локацију не изда нова грађевинска дозвола.
Решење којим се утврђује престанак важења грађевинске дозволе из става 3. овог члана доноси орган надлежан за издавање грађевинске дозволе, а по правноснажности то решење доставља Пореској управи на чијој територији се налази предметни објекат.
Брисани су ранији ст. 7. и 8. (види члан 84. Закона - 132/2014-3)
Одредбе овог члана односе се и на решења о грађевинској дозволи, односно решења о одобрењу за изградњу која су издата у складу са раније важећим законима којима је уређивана изградња објеката, пре 11. септембра 2009. године.”
Informational English translation of the quotation
A construction permit ceases to be valid if notice of works is not submitted within three years from the date on which the decision issuing the construction permit becomes final, or if notice of works is not submitted within three years from the date on which the decision amending the construction permit decision becomes final.
By way of exception to paragraph 1 of this Article, when notice of works has been submitted under Article 148 paragraph 6 of this Law, the construction permit remains valid until notice of works has been submitted for all parts of the structure.
The decision establishing that the construction permit has ceased to be valid under paragraphs 1 and 2 of this Article is issued by the authority competent to issue the construction permit.
A construction permit ceases to be valid if an occupancy permit is not issued within five years from the date on which the decision issuing the construction permit becomes final, or the decision amending the construction permit decision becomes final, except for structures under Article 133 of this Law, utility infrastructure structures built in phases, publicly owned public-purpose structures, and family residential buildings built by the investor to meet their own housing needs.
At the investor's request, the competent authority may issue a decision approving that a final construction permit remains in force for two years after the deadline prescribed in paragraph 4 of this Article, if proceedings initiated within the period in paragraph 4 establish, on the basis of the competent building inspector's record, that the structure is structurally complete.
After expiry of the period in paragraph 4 of this Article, the investor pays into the Tax Administration's account a charge equal to the property tax that would be payable under the law governing property tax for the entire structure had it been built in accordance with the construction permit, until a new construction permit is issued for that location.
The decision establishing that the construction permit has ceased to be valid under paragraph 3 of this Article is issued by the authority competent to issue the construction permit, and once final that decision is delivered to the Tax Administration in whose territory the structure concerned is located.
Former paragraphs 7 and 8 were deleted (see Article 84 of the Law - 132/2014-3).
The provisions of this Article also apply to construction permit decisions and construction approval decisions issued under earlier laws governing construction of structures, before 11 September 2009.Informational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- How much manoeuvring space must be provided in front of a garage or parking space?There is no single universal figure prescribed by the Law on Planning and Construction for every garage space. For the specific…
- A father owns the plot and his son would be the investor in an application under the unified procedure or for location conditions: is their family relationship sufficient?No. The fact that the father is the owner and the son is his relative does not in itself give the son an appropriate right to…
- What is checked or submitted with an application in the unified procedure as evidence of the appropriate right to the land?First, the appropriate right held by the investor is determined. The Planning and Construction Act lists ownership, lease of…
- What is a building line?A line on, above and below the surface of land and water up to which construction of the basic footprint of a structure is…
- What is a building complex?A whole consisting of several interconnected independent functional units or cadastral parcels, which may have different uses.
- What is included in the gross developed building area?The sum of the areas of all ABOVE-GROUND storeys of the structure, measured at floor level of all parts of the structure, using…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal