Who prescribes the structures to which the rules on contractors, supervision and technical inspection do not apply?
Answer
Informational English translation. Machine translated; not independently reviewed.
The minister responsible for construction prescribes the structures to which the provisions of the law on the contractor, responsible contractor, obligation to appoint professional supervision and technical inspection of the structure do not apply.
Original Serbian quotation
„Ministar nadležan za poslove građevinarstva propisaće na koje objekte se ne primenjuju odredbe ovog zakona o izvođaču radova, odgovornom izvođaču radova, obavezi određivanja stručnog nadzora i tehničkom pregledu objekta.”
Informational English translation of the quotation
The minister responsible for construction shall prescribe the structures to which the provisions of this Law on the contractor, responsible contractor, obligation to appoint professional supervision and technical inspection of the structure do not apply.Informational finding. An AI check is not legal or professional confirmation that the rule applies to your building. Check the full article and current official gazette.
Related questions
- How much manoeuvring space must be provided in front of a garage or parking space?There is no single universal figure prescribed by the Law on Planning and Construction for every garage space. For the specific…
- A father owns the plot and his son would be the investor in an application under the unified procedure or for location conditions: is their family relationship sufficient?No. The fact that the father is the owner and the son is his relative does not in itself give the son an appropriate right to…
- What is checked or submitted with an application in the unified procedure as evidence of the appropriate right to the land?First, the appropriate right held by the investor is determined. The Planning and Construction Act lists ownership, lease of…
- What is a building line?A line on, above and below the surface of land and water up to which construction of the basic footprint of a structure is…
- What is a building complex?A whole consisting of several interconnected independent functional units or cadastral parcels, which may have different uses.
- What is included in the gross developed building area?The sum of the areas of all ABOVE-GROUND storeys of the structure, measured at floor level of all parts of the structure, using…
The portal presents AI-checked informational findings. It does not replace official legislation, location conditions or professional review of a specific project. Portal