Categories A & B: utility conditions free of charge
For Category A and B buildings, public utility authorities issue design and connection conditions free of charge.
„Uslove za projektovanje i priključenje za objekte kategorije "A" i "B" imalac javnih ovlašćenja izdaje bez naknade.”
CEOP pravilnik, čl. 11 →
No fee notice in 3 working days = free of charge
If an authority fails to notify the fee amount through CIS within 3 working days, the conditions are treated as free of charge.
„kroz CIS obavesti o visini naknade za izdavanje tih uslova, u roku od tri radna dana od prijema automatski generisanog zahteva”
CEOP pravilnik, čl. 11 →
Corrected building permit, Art. 145 and occupancy applications
For these procedures, correct every listed defect within 30 calendar days of publication of the rejection decision. The applicant may rely on the documents and fees already submitted once.
„Ako podnosilac zahteva u roku od 30 dana od dana objavljivanja rešenja iz stava 1. ovog člana, podnese usaglašen zahtev i otkloni sve nedostatke, ne dostavlja dokumentaciju podnetu uz zahtev koji je odbačen, niti ponovo plaća administrativne takse i naknadu”
CEOP pravilnik, čl. 18, 27 i 45 →
Corrected location conditions application
The Location Conditions Regulation (Art. 6) and the Act (Art. 8đ) specify 30 days from publication. The CEOP Rulebook (Art. 8) specifies 30 working days. To meet both periods, file through CIS within 30 calendar days of publication of the rejection and address all defects. Previously submitted documents and fees may be reused once.
„u roku od 30 dana od dana objavljivanja zaključka”
Uredba o lokacijskim uslovima, čl. 6 →
· ZPI, čl. 8đ → · CEOP pravilnik, čl. 8 →
When can you reclaim the decision fee?
If the authority refuses a building or occupancy permit after you file a corrected application, you can reclaim the Republic administrative fee paid for the decision or use it when the proceedings are repeated. You have the same right if the authority refuses approval for works under Article 145.
„podnosilac zahteva ima pravo na povraćaj republičke administrativne takse za donošenje rešenja”
CEOP pravilnik, čl. 18 →
· CEOP, čl. 27 → · CEOP, čl. 45 →
Building permit validity: 3 yrs (start) / 5 yrs (occupancy)
From finality of the permit or its amendment, works must be notified within 3 years, with a special rule for parts under Art. 148(6). Occupancy must be authorised within 5 years, except for Art. 133 facilities, phased municipal infrastructure, publicly owned public-use facilities and family housing built for the investor’s own housing needs. Upon timely application the authority may grant 2 more years if the inspector records structural completion. For buildings whose occupancy permit deadline had already expired, Art. 41 of the 91/2025 amendments allows the authority to issue the permit within two additional years from the effective date of those amendments.
„Грађевинска дозвола престаје да важи ако се не изврши пријава радова у року од три године од дана правноснажности решења којим је издата грађевинска дозвола”
ZPI, čl. 140 →
· ZPI 91/2025, čl. 41 →
Objection to location conditions: 3 days
The applicant has 3 days from delivery. If delivery is on Wednesday and the authority is closed on Saturday and Sunday, the deadline expires on Monday if it is a working day (General Administrative Procedure Act, Art. 80). A planning inspector has a separate period of up to 30 days from issuance to object to conditions that conflict with the law or plan. For a municipal decision, file through the issuing authority to the municipal or city council. For a provincial decision, Art. 56 of the Act names the Government via the Ministry, while Art. 14 of the Rulebook and Art. 15 of the Regulation name the provincial executive via the provincial authority. Check the remedy instructions in the decision promptly.
„podnosilac zahteva za izdavanje lokacijskih uslova može izjaviti prigovor nadležnom opštinskom, odnosno gradskom veću, preko nadležnog organa, u roku od tri dana od dana njihovog dostavljanja.”
CEOP pravilnik, čl. 14 →
· ZPI, čl. 56 → · Uredba, čl. 15 →
Building permit, Article 145 and occupancy decisions
A local authority decision may be appealed through the first-instance authority within 8 days of delivery. For a first-instance decision by the Ministry or competent provincial authority, administrative court proceedings may be initiated within 30 days of delivery.
„može se preko prvostepenog organa, izjaviti žalba u roku od osam dana od dana dostavljanja”
CEOP pravilnik, čl. 21, 27 i 48 →
Demolition permit appeal: 15 days
A local demolition permit decision may be appealed within 15 days of delivery. Ministry or provincial decisions may be challenged in administrative court within 30 days of delivery (Act, Art. 168).
„Na rešenje iz stava 3. ovog člana može se izjaviti žalba u roku od 15 dana od dana dostavljanja rešenja, u skladu sa Zakonom.”
CEOP pravilnik, čl. 51a →