CEOP deadlines & fees in Serbia

Interactive overview of statutory deadlines by CEOP phase (location info, location conditions, building permit, Art. 145, work commencement, occupancy permit, cadastre) plus fee obligations and exemptions.

These deadlines and fees are for information only. Check the deadline for your case in the decision you received. File the application electronically through CIS, where you will also receive payment instructions. In Serbia, contact the city or municipal planning and construction office where the property is located. For projects under provincial or national jurisdiction, contact the responsible provincial authority or ministry. In Belgrade, check whether to contact your city municipality or the City Secretariat. Tariff items and official rates ↓

Legal basis & calculation formula

Official texts in the Serbian Legal Information System · Electronic permitting rulebook · Location Conditions Regulation · Planning and Construction Act

The sum covers the numerical periods of the selected steps. Design, construction, suspensions, inspections and time to finality are separate. Under Art. 8d of the Act, receipt of a works notice is acknowledged without delay, with an exception for checking payment security. The sum uses the Art. 32 Rulebook period for checking the notice.

A period stated in days starts the day after delivery, publication or the other specified event. Calendar-day periods include days when the authority is closed. If the last day falls on such a day, the period ends at the end of the next working day. General Administrative Procedure Act, Art. 80 →

Legal sources: CEOP Rulebook (Sl. glasnik RS, br. 96/2023, 33/2026) · Planning & Construction Act (72/2009 … 91/2025, 80/2026). Each period runs from the event specified for that step. For current RSD fees, consult the Republic Administrative Fees Act and the APR fee decision.

  1. 1

    Location information (optional, pre-design)

    8 days from filing with the competent authority

    The competent authority charges its actual issuance costs. On request, a notary, a legal entity or a sole trader registered to prepare spatial and urban plans may also issue the information. The eight-day period applies to the competent authority.

    Guide (in Serbian): Informacija o lokaciji

    ZPI, čl. 53
    „Информацију о локацији издаје орган надлежан за издавање локацијских услова у року од осам дана од дана подношења захтева, уз накнаду стварних трошкова издавања те информације.”
    Read full article →
  2. 2

    Authority requests conditions from public bodies

    5 working days from receipt of the location conditions application

    Where the plan does not supply the conditions, the authority requests them on the applicant’s behalf.

    Guide (in Serbian): Uslovi imalaca javnih ovlašćenja (IJO)

    ZPI, čl. 8b
    „у року од пет радних дана од дана пријема захтева за издавање локацијских услова”
    Read full article →
  3. 3

    Obtaining public utility & authority conditions

    15 days from receipt of the CIS request (30 days for Art. 133 facilities)

    Conditions are free for A and B. Where fees apply, the public body must notify the amount through CIS within 3 working days of receipt. The Arts. 52 and 53 procedures use 15 days even for Art. 133. If the applicant requested prior approval of costs, the clock pauses until acceptance. Without acceptance through CIS the procedure is discontinued at the earliest deadline set by a public body or, at the latest, 30 days after the pause began.

    Guide (in Serbian): Uslovi imalaca javnih ovlašćenja (IJO)

    CEOP pravilnik, čl. 11
    „Imalac javnih ovlašćenja je dužan da uslove iz stava 1. ovog člana, dostavi u roku od 15 dana od dana prijema automatski generisanog zahteva kroz CIS, a za objekte iz člana 133. Zakona u roku od 30 dana od dana prijema automatski generisanog zahteva kroz CIS”
    Read full article →
  4. 4

    Issuance of location conditions after utility responses

    5 working days after delivery of all necessary conditions and data

    Administrative fee + CEOP fee paid on filing (Art. 6).

    Guide (in Serbian): Lokacijski uslovi

    CEOP pravilnik, čl. 13
    „Nadležni organ je dužan da izda lokacijske uslove u skladu sa Zakonom i uredbom koja uređuje izdavanje lokacijskih uslova, u roku od pet radnih dana od dana dostavljanja uslova za projektovanje i priključenje”
    Read full article →
  5. 5

    Building permit issuance

    5 working days from filing the application

    Administrative fee and CEOP fee. If a land development contribution is assessed in the permit, submit proof of full payment or of the first instalment with the commencement notice, as the permit specifies.

    Guide (in Serbian): Građevinska dozvola

    CEOP pravilnik, čl. 19
    „Nadležni organ, ako su ispunjeni uslovi propisani Zakonom i članom 17. ovog pravilnika, donosi rešenje o građevinskoj dozvoli u roku od pet radnih dana od dana podnošenja zahteva.”
    Read full article →
  6. 6

    Notice of commencement of works

    Within 5 working days to check the notice (Art. 32)

    Administrative fee and CEOP fee. Attach third-party liability insurance and the standard electricity connection contract if provided with the location conditions. For an assessed contribution payable in instalments, attach proof of the first payment. Security is also required if gross floor area exceeds 200 m² or the building has more than two dwellings (Art. 31).

    Guide (in Serbian): Prijava radova

    CEOP pravilnik, čl. 31–32; ZPI, čl. 8d i 148
    „Nadležni organ u roku od pet radnih dana potvrđuje prijavu radova”
    Read full article →
  7. 7

    Foundation & structural completion notifications

    Confirmed without delay (forwarded to inspection within 3 days)

    Each declaration includes its survey and proof of payment. The authority acknowledges a complete notice without delay. Inspection takes place within 10 working days of each notification, for both foundations and structural completion.

    Guide (in Serbian): Prijava završetka temelja · Prijava završetka objekta u konstruktivnom smislu

    CEOP pravilnik, čl. 34–36
    „Izvođač radova podnosi nadležnom organu izjavu o završetku izgradnje objekta u konstruktivnom smislu kroz CIS, odmah po završetku te faze izgradnje.”
    Read full article →
  8. 8

    Utility & infrastructure connection

    3 working days to forward + 15 days to connect, subject to conditions

    The connection period runs from receipt if the connection conditions are met. If payment after final billing was selected, it starts the day after proof of payment is submitted. For electricity, the deadline cannot precede the agreed date for completing the connection works.

    Guide (in Serbian): Priključenje objekta na infrastrukturu

    CEOP pravilnik, čl. 40–42
    „imalac javnih ovlašćenja je dužan da izvrši priključenje objekta na komunalnu i drugu infrastrukturu i da o tome obavesti nadležni organ u roku od 15 dana od dana prijema zahteva za priključenje”
    Read full article →
  9. 9

    Occupancy permit issuance

    5 working days from filing, subject to statutory pauses

    Administrative and CEOP fees with the prescribed supporting documents. The clock stops while the cadastre checks the survey (Art. 44). In the discrepancy cases under Art. 8d of the Act, the period runs from delivery of the reconciled documentation.

    Guide (in Serbian): Tehnički pregled · Upotrebna dozvola

    CEOP pravilnik, čl. 46 i ZPI čl. 158
    „Ako su ispunjeni formalni uslovi iz člana 44. ovog pravilnika, nadležni organ donosi rešenje o upotrebnoj dozvoli u roku od pet radnih dana od dana podnošenja zahteva, u skladu sa Zakonom.”
    Read full article →
  10. 10

    Forwarding to cadastre & ownership registration (ex officio)

    5 working days (forwarding, Art. 49) + 7 days (RGZ entry, Art. 50)

    The authority forwards the documents within 5 working days of the occupancy permit becoming final. RGZ issues its ownership registration decision for the building or its units within 7 days of receiving the documents. RGZ assesses the cadastral fee.

    Guide (in Serbian): Upis završenog objekta u katastar

    CEOP pravilnik, čl. 49–50
    „Organ nadležan za poslove državnog premera i katastra, u roku od sedam dana, od dana dostavljanja dokumenata iz člana 49. ovog pravilnika, donosi rešenje kojim vrši upis prava svojine na objektu”
    Read full article →

What fees apply to a filing?

APR registry fee

For location conditions, building permits and occupancy permits, choose A/B or V/G. To amend existing location conditions, a building permit, an Article 145 approval or a temporary building permit, APR charges the same registry fee as for issuing that act.

If an application is rejected for formal defects, you can reuse the registry fee once by filing a corrected application in time and addressing all defects. Commencement, foundation completion and structural completion are separate filings. CIS provides payment instructions when you file.

APR — current CEOP fees → · Open CIS →

Republic administrative fee

Check tariff item 1 and its exceptions for the application itself. For the act issued, look up the tariff item and building category in the current indexed rates. Articles 18 and 19 of the Act list exempt applicants, documents and procedures.

  • 164 — confirmation of foundation or structural completion
  • 165 — issue or amendment of a building permit or Article 145 approval, and issue of a temporary building permit or permit for preparatory works
  • 170 — occupancy permit
  • 171a — work commencement confirmation
  • 171b — location information issued by the competent authority
  • 171v — location conditions issued by a Republic authority
Ministry of Finance — Act and current indexed rates →

Local fees, connections and land development

Check the municipal tariff for the specific filing. The A/B exemption covers the issue of design and connection conditions. Carrying out the physical connection is priced separately. Where a land development contribution is assessed, the permit specifies the payment terms.

Belgrade land development contribution →

Key rules on fees, exemptions, validity & appeals

Categories A & B: utility conditions free of charge

For Category A and B buildings, public utility authorities issue design and connection conditions free of charge.

„Uslove za projektovanje i priključenje za objekte kategorije "A" i "B" imalac javnih ovlašćenja izdaje bez naknade.”
CEOP pravilnik, čl. 11 →

No fee notice in 3 working days = free of charge

If an authority fails to notify the fee amount through CIS within 3 working days, the conditions are treated as free of charge.

„kroz CIS obavesti o visini naknade za izdavanje tih uslova, u roku od tri radna dana od prijema automatski generisanog zahteva”
CEOP pravilnik, čl. 11 →

Corrected building permit, Art. 145 and occupancy applications

For these procedures, correct every listed defect within 30 calendar days of publication of the rejection decision. The applicant may rely on the documents and fees already submitted once.

„Ako podnosilac zahteva u roku od 30 dana od dana objavljivanja rešenja iz stava 1. ovog člana, podnese usaglašen zahtev i otkloni sve nedostatke, ne dostavlja dokumentaciju podnetu uz zahtev koji je odbačen, niti ponovo plaća administrativne takse i naknadu”
CEOP pravilnik, čl. 18, 27 i 45 →

Corrected location conditions application

The Location Conditions Regulation (Art. 6) and the Act (Art. 8đ) specify 30 days from publication. The CEOP Rulebook (Art. 8) specifies 30 working days. To meet both periods, file through CIS within 30 calendar days of publication of the rejection and address all defects. Previously submitted documents and fees may be reused once.

„u roku od 30 dana od dana objavljivanja zaključka”
Uredba o lokacijskim uslovima, čl. 6 → · ZPI, čl. 8đ → · CEOP pravilnik, čl. 8 →

When can you reclaim the decision fee?

If the authority refuses a building or occupancy permit after you file a corrected application, you can reclaim the Republic administrative fee paid for the decision or use it when the proceedings are repeated. You have the same right if the authority refuses approval for works under Article 145.

„podnosilac zahteva ima pravo na povraćaj republičke administrativne takse za donošenje rešenja”
CEOP pravilnik, čl. 18 → · CEOP, čl. 27 → · CEOP, čl. 45 →

Building permit validity: 3 yrs (start) / 5 yrs (occupancy)

From finality of the permit or its amendment, works must be notified within 3 years, with a special rule for parts under Art. 148(6). Occupancy must be authorised within 5 years, except for Art. 133 facilities, phased municipal infrastructure, publicly owned public-use facilities and family housing built for the investor’s own housing needs. Upon timely application the authority may grant 2 more years if the inspector records structural completion. For buildings whose occupancy permit deadline had already expired, Art. 41 of the 91/2025 amendments allows the authority to issue the permit within two additional years from the effective date of those amendments.

„Грађевинска дозвола престаје да важи ако се не изврши пријава радова у року од три године од дана правноснажности решења којим је издата грађевинска дозвола”
ZPI, čl. 140 → · ZPI 91/2025, čl. 41 →

Objection to location conditions: 3 days

The applicant has 3 days from delivery. If delivery is on Wednesday and the authority is closed on Saturday and Sunday, the deadline expires on Monday if it is a working day (General Administrative Procedure Act, Art. 80). A planning inspector has a separate period of up to 30 days from issuance to object to conditions that conflict with the law or plan. For a municipal decision, file through the issuing authority to the municipal or city council. For a provincial decision, Art. 56 of the Act names the Government via the Ministry, while Art. 14 of the Rulebook and Art. 15 of the Regulation name the provincial executive via the provincial authority. Check the remedy instructions in the decision promptly.

„podnosilac zahteva za izdavanje lokacijskih uslova može izjaviti prigovor nadležnom opštinskom, odnosno gradskom veću, preko nadležnog organa, u roku od tri dana od dana njihovog dostavljanja.”
CEOP pravilnik, čl. 14 → · ZPI, čl. 56 → · Uredba, čl. 15 →

Building permit, Article 145 and occupancy decisions

A local authority decision may be appealed through the first-instance authority within 8 days of delivery. For a first-instance decision by the Ministry or competent provincial authority, administrative court proceedings may be initiated within 30 days of delivery.

„može se preko prvostepenog organa, izjaviti žalba u roku od osam dana od dana dostavljanja”
CEOP pravilnik, čl. 21, 27 i 48 →

Demolition permit appeal: 15 days

A local demolition permit decision may be appealed within 15 days of delivery. Ministry or provincial decisions may be challenged in administrative court within 30 days of delivery (Act, Art. 168).

„Na rešenje iz stava 3. ovog člana može se izjaviti žalba u roku od 15 dana od dana dostavljanja rešenja, u skladu sa Zakonom.”
CEOP pravilnik, čl. 51a →

Frequently asked questions

How long does a building permit take under CEOP?

The authority decides on a complete building permit application within 5 working days of filing (Art. 19). Location conditions, preparing the design and notifying works are separate steps.

Which buildings qualify for free design and connection conditions?

Public bodies issue these conditions free of charge for categories A and B (Art. 11). The actual connection is charged separately when applicable.

Do I pay filing fees again after a formal rejection?

You can reuse the fees once if you file a corrected application and remove all defects. Count 30 calendar days from publication of the rejection. For location conditions, Art. 6 of the Regulation and Art. 8đ of the Act state 30 days, while Art. 8 of the Rulebook states 30 working days. Filing within 30 calendar days meets both periods.

How long is a building permit valid?

From finality of the permit or its amendment, works must be notified within 3 years, with a special rule for parts under Art. 148(6). Occupancy must be authorised within 5 years, except for Art. 133 facilities, phased municipal infrastructure, publicly owned public-use facilities and family housing built for the investor’s own housing needs. Upon timely application the authority may grant 2 more years if the inspector records structural completion. For buildings whose occupancy permit deadline had already expired, Art. 41 of the 91/2025 amendments allows the authority to issue the permit within two additional years from the effective date of those amendments.